News Highlights Summary Acquisition
Agreement
Location
and Climate
Land Status
Exploration
History
Geology Exploration
Potential
Gold Resources Environmental/
Regulatory

UPDATED AUGUST-18-04

Environmental/Regulatory


The United States Forest Service (USFS) would be the lead regulatory agency on the federal level that is responsible for review and approval of mining activities at Quartz Mountain. The USFS´s mineral permitting program is triggered by the submittal of a Notice of Intent (NOI) to mine, and detailed Plan of Operations (POO). A POO is usually developed following the completion of a detailed Feasibility Study that outlines the optimum mining and processing method(s) and the specifics of a proposed project. The USFS is responsible for reviewing potential environmental impacts of the proposed project, and if necessary, the development of project-specific mitigation and reclamation. In addition, the USFS is responsible for soliciting public participation (comment and review) on the proposed project. Depending upon the level of impact and the amount of public interest, the USFS recommends that an Environmental Assessment (EA) or an Environmental Impact Statement (EIS) be performed. The key differences between these evaluations is the amount of public participation, the time necessary to obtain approval, and the amount of resources needed to obtain approval.

The Quartz Mountain Project is characterized as a development project that has undergone considerable exploration and a Feasibility Study level evaluation of an open pit(s) mine with heap leach processing in the mid-to-late 1980´s. Environmental baselines and monitoring at Quartz Mountain were initiated by previous owners in the late 1980´s. These activities were directed by SRK Consulting´s Reno Office. Many local specialists were used to support this effort. These reports are valuable in assessing impacts and making recommendations for future work. The reports also provide valuable information that may be used by Seabridge in limiting liability as well as supporting future efforts should Seabridge decide to proceed with development of a particular development plan at the Quartz Mountain Project.

To further study the permitting issues at Quartz Mountain, Seabridge retained Gochnour & Associates of Parker, Colorado (“Gochnour”) to undertake an environmental review and regulatory permitting due diligence on Quartz Mountain. The report of Gochnour is entitled “Quartz Mountain Project; Permitting/Environmental Report” (the “QMP P/E Report”) and dated November 28, 2001. The following material was drawn from the QMP P/E Report. The Gochnour study examined various potential development scenarios including an open pit and/or underground mining operations. Processing alternatives include on-site milling and/or heap leach technology utilizing cyanide, and off-site processing (toll milling). Waste disposal alternatives include overburden stockpiles adjacent to the orebody (under an open pit scenario). With an underground or combination open-pit/underground mining scenario, waste could be used as backfill and/or stockpiled on the surface, adjacent to mining operations. Each Alternative would require the development of a different reclamation strategy.

Gochnour concluded that each of the development scenarios are permittable under current federal and state law. To complete the permitting process, Gochnour estimates that the open-pit scenario would take 3-5 years to permit once a Plan of Operations (“POO”) had been submitted. Gochnour estimated the permitting time frame for the underground scenarios at 2-3 years after the POO was submitted.